Spiral tube equipment spiral tube equipment

- Oct 24, 2019-

1. Adjustment: When determining the size of the finished tube, the change according to the diameter and thickness of the tube.


1.1. Uncoiler: The plate width change adjustment positioning ring is fixed on the disk.


1.2. Feeding pinch leveling machine: The width of the plate is adjusted to adjust the vertical roll, and the thickness of the plate is manually adjusted to adjust the amount of the leveling roll.


1.3. Shear butt welding: plate thickness variation adjusts the cutting edge clearance.


1.4. Vertical roller device: The width of the plate is manually adjusted to adjust the opening degree of the vertical roller.


1.5. Pre-bend guide: The plate width changes manually adjust the pre-bending device and the guide strip.


1.6. Molding machine: tube diameter change, change the adjustment slider, adjust 1#, 3# forming rolls.


1.7. Rear axle: The pipe diameter changes the output bracket, the output roller and the support under the blanking device.


2 test drive:


2.1 Preparation before commissioning: Before and after the test, each electromechanical equipment should be carefully and thoroughly inspected. It is true that the following conditions are met before the test run.


2.1.1. The test area is cleaned up with all debris and other obstacles affecting the test run.


2.1.2. The components of the equipment are fully installed, all the anchor bolts and coupling bolts are tightened, firm and reliable, and various protective devices are installed.


2.1.3. For the transmission system such as the reduction gear box and the coupling, fill the oil according to the instructions.


2.1.4. The required amount of oil and oil are loaded into the reduction cabinet.


2.1.5. The hydraulic seal meets the sealing requirements and there is a leak.


2.1.6. Electrical equipment is good.


2.1.7. Before the test, apply the hand-cranked car, the rotation is flexible, there is no jamming phenomenon, and it is confirmed that there is no problem before the test can be carried out.


2.1.8. Do a good job in the organization of the test run. When commissioning the test, you should be directed by a special person. Special personnel should be responsible for the operation. If you are involved in commissioning, you should wear the logo. The test record should be made by a special person. Persons not involved in the test run should be evacuated from the scene.


2.1.9. If abnormality is found during the test run, it is necessary to stop immediately.


Related Products